Re: [PATCH v2] nvme: stop asynchronous event work before ANA teardown
From: Keith Busch
Date: Fri Nov 06 2026 - 11:51:24 EST
On Thu, 5 Nov 2026 19:41:49 +0800, Yaohan Li wrote:
> NVMe ANA work has several producers, including ANA AER completion,
> namespace scanning and failover processing.
>
> An AER completion can queue ana_work for an ANA notice and can
> separately queue async_event_work, which sends the AEN uevent and
> submits the next asynchronous event request. These work items access
> controller-owned state during asynchronous processing.
>
> [...]
Thanks, applied to nvme-7.4.
[1/1] nvme: stop asynchronous event work before ANA teardown
commit: 9b657c565984f28976b1e471e3ce2f81cc269238
--
Keith Busch <kbusch@xxxxxxxxxx>